Follow-up duration is calculated automatically from your data if the following variables are available:

  • Inclusion date
  • Last follow-up date


To convert this duration in months, we divide the number of days between the 2 dates by 30.5


FU duration (months) = (Last follow-up date - Inclusion date) / 30.5